PROJECT MONITORING
Barbu Vacarescu 102 Residential
| client | location | size | duration | services |
|---|---|---|---|---|
| CABA INNOVATIVE CONSTRUCT S.R.L. | str. Barbu Vacarescu, nr. 102, Sector 2, Bucharest, Romania | Block | 3B+G+9F | 49834 sqm | 03.20218 -12.2020 | 31 months | Project Monitoring |
Alphaville
| client | location | size | duration | services |
|---|---|---|---|---|
| ALPHAVILLE ARENA PATRU S.A. | Strada Stadionului, numarul 15, Brasov, Romania | 3 Blocks | 306 apartments | B+G+11F | 28083 sqm | 07.2018 - 09.2021 | 39 months | Project Monitoring |
SEA ONE MAMAIA
| client | location | size | duration | services |
|---|---|---|---|---|
| EURO VIAL RESIDENCE S.R.L. | Bulevardul Mamaia Nord, nr., zona Mamaia Nord, orasul Navodari, Jud. Constanta, Romania | 2 Blocks | 306 apartments | G+9F | 14420 sqm | 11.2018-08.2021 | 32 months | Project Monitoring |
SEMA PARK
| client | location | size | duration | services |
|---|---|---|---|---|
| Europolis Real Estate Asset Management GMBH Austria | Bucharest, Romania | 2B+G+8F | 50000 sqm | 12.2006 - 12.2008 | 24 months | Monitoring, Technical Due Diligence |
City Building
| client | location | size | duration | services |
|---|---|---|---|---|
| Europolis Real Estate Asset Management GMBH Austria | Bucharest, Romania | 35000 sqm | - | Monitoring, Technical Due Diligence |
Court Yard Park
| client | location | size | duration | services |
|---|---|---|---|---|
| Europolis Real Estate Asset Management GMBH Austria | Bucharest, Romania | 15000 sqm | - | Monitoring, Technical Due Diligence |
Cefin Logistic Park Militari
| client | location | size | duration | services |
|---|---|---|---|---|
| Europolis Real Estate Asset Management GMBH Austria | Bucharest, Romania | 7 Logistic building & infrastructure | 500.000 sqm | 01.2007 - 12.2007 | 24 months | Monitoring, Technical Due Diligence |
Cefin Logistic Park Arad
| client | location | size | duration | services |
|---|---|---|---|---|
| Europolis Real Estate Asset Management GMBH Austria | Arad, Romania | G + 1F partial Warehouse, G + 3F Multifunctional office building Access road, parking and water tank | 50717 sqm | 07.2007 - 12.2008 | 18 months | Monitoring, Technical Due Diligence |
Asmita Gardens
| client | location | size | duration | services |
|---|---|---|---|---|
| Charlemagne Capital | Bucharest, Romania | Blocks | 760 apartments per block | 142766 sqm | 07.2007 - 12.2008 | 18 months | Monitoring; actions in order to obtain the utilities permits (sewage, electricity, gas) with the reducing the costs with approximate 4 million EURO |
Barbu Vacarescu Residential Complex
| client | location | size | duration | services |
|---|---|---|---|---|
| CABA Innovative Construct | Bucharest, Romania | Block | 285 apartments | 49,834 sqm | 02.2018 - 12.2020 | 34 months | Monitoring |
Funshop Park Rosiorii
| client | location | size | duration | services |
|---|---|---|---|---|
| SCALLIER Investment | Rosiorii de Vede, Romania | Retail Park | 6396 sqm | 03.2021 - 12.2021 | 8 months | Monitoring |
alphaville Arena Complex
| client | location | size | duration | services |
|---|---|---|---|---|
| ALPHAVILLE Arena Patru | Brasov, Romania | Blocks | 305 apartments | 31929 sqm | 07.2018 - 10.2021 | 40 months | Monitoring |
Strach Factory
| client | location | size | duration | services |
|---|---|---|---|---|
| OMNIA EUROPE | Medgidia, Romania | Strach Factory & Related Installations | 64601 sqm | 11.2019 - 11.2021 | 25 months | Monitoring |
Vasile Lascar Residential Multifunctional
| client | location | size | duration | services |
|---|---|---|---|---|
| NAKATOMI Development | Bucharest, Romania | Blocks | 349 apartments | 48284 sqm | 11.2018 - 12.2020 | 25 months | Monitoring |
Agora Floreasca
| client | location | size | duration | services |
|---|---|---|---|---|
| NGR ASSET | Bucharest, Romania | Commercial Complex | 8420 sqm | 02.2017 - 11.2019 | 34 months | Monitoring |